2016 CFSEI DESIGN EXCELLENCE
AWARD WINNERS

FIRST PLACE

BASE DESIGN GROUP, INC. – MEDITECH FOXBOROUGH OFFICE AND CONFERENCE CENTER
FOXBOROUGH, MA

Meditech Foxborough Office and Conference Center
1 Constitution Way
Foxborough, MA 02035

Completed: June 2015
Construction Cost: $35 million

Owner: MEDITECH
Architect of Record: Payette Associates Inc.
Engineer of Record for Structural Work: Goldstein-Milano LLC
Cold-Formed Steel Specialty Engineer:
Base Design Group, Inc.
Cold-Formed Steel Specialty Contractor: Commercial Drywall & Construction Co. Inc.  
Award Entry Submitted by: Nate Bacon, P.E., Base Design Group, Inc.

Project Summary Details

SECOND PLACE

EXCEL ENGINEERING, INC. – THE WHARF
WASHINGTON, DC

The Wharf – 525 Water
525 Water Street, SW
Washington, DC 20024

Completed: December 2015
Construction Cost: $30 million

Owner: RWP, LLC
Architect of Record: SK&I Architectural Design Group, LLC
Engineer of Record for Structural Work: Brian McSweeney, Ehlert Bryan  
Cold-Formed Steel Specialty Engineer:
Joe Wilkum, Excel Engineering, Inc.
Cold-Formed Steel Specialty Contractor: Trevor Wyman, FrameCo, Inc.  
Award Entry Submitted by: Bill Wilde, Excel Engineering, Inc.

Project Summary Details

THIRD PLACE

CLARKDIETRICH ENGINEERING SERVICES, LLC – WILLIAM P. HOBBY AIRPORT EXPANSION PROJECT
HOUSTON, TX

William P. Hobby Airport
7748 Airport Blvd.
Houston, TX 77061

Completed: October 2015
Construction Cost: $156 million

Owner: Southwest Airlines
Architect of Record: Corgan Associates, Inc.
Engineer of Record for Structural Work: Raxit Patel, Henderson & Rogers, Inc./ Rogers Moore Engineers, Inc.
Cold-Formed Steel Specialty Engineer:
Wesley Burghardt/Bill Ewing/Brent Owens/Kale McDaniel, ClarkDietrich Engineering Services, LLC
Cold-Formed Steel Specialty Contractor: Texas Exterior Systems
Award Entry Submitted by:Wesley Burghardt, ClarkDietrich Engineering Services, LLC

Project Summary Details

 

2015 CFSEI DESIGN EXCELLENCE
AWARD WINNERS

FIRST PLACE

CLARKDIETRICH – AQ RITTENHOUSE
PHILADELPHIA, PA

RittenhouseAQ Rittenhouse
2021 Chestnut Street
Philadelphia, PA 19103

Completed: December 2014
Construction Cost: $33 million

Owner: Aquinas Realty Partners
Architect of Record: Stampfl Associates
Engineer of Record for Structural Work: Jannis Vacca, P.E.,
The Harman Group
Cold-Formed Steel Specialty Engineer: Wesley Burghardt,
ClarkDietrich Engineering (Lead Engineer)
Cold-Formed Steel Specialty Contractor: Anthony Faranda,
Clemens Construction Company, Inc.

Project Summary Details

SECOND PLACE

DSi ENGINEERING, LLC – ELAN WESTSIDE APARTMENTS
ATLANTA, GA

Westside ApartmentsElan Westside Apartments
691 14th Street
Atlanta, GA 30318

Completed: April 2014
Construction Cost: $45 million

Owner: Greystar Apartments
Architect of Record: Surber Barber Choate & Hertlein
Engineer of Record for Structural Work: Sergio LeGuizamon, Browder + LeGuizamon & Associates, Inc.
Cold-Formed Steel Specialty Engineer: Steve Haddad, DSi Engineering, LLC
Cold-Formed Steel Specialty Contractor: Mitch Hughes, DSi Structures, LLC

Project Summary Details

THIRD PLACE

CEMCO – PLAZA AT PEARL CITY ASSISTED LIVING FACILITY
PEARL CITY, HI

Plaza at Pearl CityPlaza at Pearl City Assisted Living Facility
1082 Kuala Street
Pearl City, HI 96782

Completed: September 2014
Construction Cost: $46 million

Owner: Plaza at Pearl City/MW Group
Architect of Record: Wattenbarger Architecture
Engineer of Record for Structural Work: Steven Baldridge, Base Engineering
Cold-Formed Steel Specialty Engineer: Steven Baldridge, Base Engineering
Cold-Formed Steel Specialty Contractor: Emil Bete, Group Builders

Project Summary Details

 

2014 CFSEI DESIGN EXCELLENCE

AWARD WINNER

DSi ENGINEERING, LLC – BARROW ELEMENTARY SCHOOL
ATHENS, GA

Barrow Elementary SchoolBarrow Elementary School
100 Pinecrest Drive
Athens, Georgia 30605

Completed: August 2013
Construction Cost: $1 million (steel portion)

Owner: Clarke County School District
Architect of Record: Larry N. Pope, AIA SP Design Group, Architects and Engineers
Engineer of Record for Structural Work: Thad Gilliam, P.E., LEED AP – BD+C, GW Design Group, LLC
Cold-Formed Steel Specialty Engineer: Steve Haddad, DSi Engineering, LLC
Cold-Formed Steel Specialty Contractor: Danny Odom, Odom Construction Systems, Inc.
Construction Manager: David Moore, Piedmont Construction Group, LLC


Project Summary Details